Monday, December 26, 2011

70-178 Q & A / Study Guide

MCTS Training, MCITP Trainnig

Best Microsoft MCTS Certification, Microsoft MCITP Training at certkingdom.com


QUESTION 1
You work as a Project Manager at Certkingdom.com. You are using Microsoft Project Professional 2010 to
manage a project.
You notice that a section of the project is located in the wrong phase. The section includes a
summary task that contains eight subtasks and two milestones. You need to move the section
complete with the summary tasks and milestones to a different project phase. You want the Work
Breakdown Structure (WBS) numbering to be updated to match the destination phase.
Which of the following actions should you take?

A. You should select the summary task and select Change Working Time on the Project ribbon.
B. You should select the summary task and modify the start and finish dates.
C. You should open the properties of the summary task, select the Advanced tab and configure
the WBS code.
D. You should select the section including the summary task and milestones and click the Move
task option.
E. You should select the summary task and drag it to the correct phase.

Answer: B

Explanation:


QUESTION 2
Your work at Certkingdom.com includes management of projects using Microsoft Project Professional
2010.
You have several tasks in your project schedule. The tasks are a mix of active and inactive tasks
that are automatically or manually scheduled. Some tasks are summary tasks that include
subtasks. The tasks are listed using different text colors and fonts including bold, underline and
strikethrough fonts.
A new member of the project team uses Microsoft Office Project Professional 2007. He asks you
to save the project as a Project 2007 project until his version of Project is upgraded to 2010.
As a result of some features of the task list not being compatible with Project 2007, you would like
to complete the task without creating any new milestones.
Which of the following actions should you take?

A. You should alter all the tasks to be Manually Scheduled tasks.
B. You should alter all the tasks to be Auto Scheduled tasks.
C. You should alter the font of all tasks listed with a strikethrough font.
D. You should alter the font of all tasks listed with a bold font.

Answer: C

Explanation:


QUESTION 3
You work as a Project Manager at Certkingdom.com. You are using Microsoft Project Professional 2010 to
manage multiple projects.
Some resources are shared and work is distributed between the projects. You have received
instructions to modify the workload for some of the shared resources.
Which two of the following actions should you take? (Choose two.)

A. You should consider inserting the existing project schedules into a blank project as subprojects.
B. You should consider select the Links Between Projects option.
C. You should consider opening each existing project schedule and select the shared resource
pool.
D. You should consider enabling the Load Summary Resource Assignments option.
E. You should consider selecting the Level Resource function and select the required resources.
F. You should consider selecting the Level All function.

Answer: A,E

Explanation:


QUESTION 4
Your work at Certkingdom.com includes management of projects using Microsoft Project Professional
2010. You are working on a Software System Development project.
You have a task named Business Requirements Definition that is scheduled to be completed by
20th July.
The constraint type for all tasks listed in the project schedule is configured as “As Soon As
Possible”.
The project team members inform you that the Business Requirements Definition task will be
completed by 15th July. You want the default Gantt chart to show 20th July as the completion date
instead of 15th July.
Which of the following actions should you take?

A. Open the task information window and enter 20th July in the Constraint date field.
B. Open the task information window and enter 20th July in the Deadline date field.
C. Open the task information window and select the Fixed Units option in the Task Type field.
D. Open the task information window and enter 20th July in the Finish date field.

Answer: B

Explanation:


QUESTION 5
You work as a Project Manager at Certkingdom.com. You are using Microsoft Project Professional 2010 to
manage a new project.
The project will be divided into five major phases. The time that each phase will take is still being
calculated but the entire project needs to be completed within 6 months.
How should you configure the project to indicate that the entire duration will be 180 days?

A. You should configure five summary tasks each with a duration of 36 days.
B. You should set the Status Date to 180 days into the future.
C. You should enter the project timescale in the project calendar.
D. You should create a single summary task with the manually scheduled option.

Answer: C

Explanation:

MCTS Training, MCITP Trainnig

Best Microsoft MCTS Certification, Microsoft MCITP Training at certkingdom.com

No comments:

Post a Comment